The incinerator to be fully assembled wired and logic function tested in the factory, prior to dispatch.
– One high flue gas temperature indicator/alarm to provide an audio/visual warning in the event of high flue gas
temperatures occurring in two stages:-
First stage audible alarm, second stage incinerator shutdown, with one voltage free contact for connection to a
remote alarm system.
– Flexible wire control linkages to bring under fire air, overfire air and burner slide plate control to front of
incinerator.
– One fire protection system, comprising fusible links over burners, deadweight fire valve, electrically
interlocked with incinerator controls.
– Special feeding door with thermal lock to protect the operator from accident.
2.2 PRIMARY CHAMBER
connections for primary air supply, start-up burner, thermal reactor, water injection and all necessary measuring probe
sockets.
refractory suitable for a continuous service temperature of 1500 deg. C. This lining shall be separated from the steel
construction by a second layer of insulation. Heat resistant cast steel plates with many fine holes shall be lied over
the refractory lined floor of the unit with a space between the two.
2.3 THERMAL REACTOR
outlet, the secondary and tertiary air supply, the reactor burner and all the required measuring probes.